Introduction to an estimate
Last updated: 2023-03-05
This section explains the organization of a engineer's estimate. The section is broken down into these key areas:
- Export project from Preconstruction for Estimator
- Creating an estimate in Estimator – Entering project estimate header information
- Creating an estimate in Estimator – Creating project categories
- Creating an estimate in Estimator – Adding bid items
- Import estimate into Preconstruction
- Creating an estimate in Preconstruction – Updating the project
- Creating an estimate in Preconstruction – Categories
- Creating an estimate in Preconstruction – Items
- Creating a proposal for PS&E Submittal
Info: Throughout the AWP Preconstruction application, PS&E is referenced as PSE . The AASHTOWare Project application does not recognize some special characters including the “&” sign. Occasionally when referencing a PS&E process within the application, PSE will be used instead in this documentation.
A bid item is a product or service to be provided by a contractor as part of a construction project. Bid items fall into several types:
- Standard Bid Items: These are bid items that have been formally established and are applicable to a wide variety of projects. Standard bid items are listed and fully explained in the “Standard Specifications for Highway and Structure Construction”.
- Standardized Special Bid Items (STSPs): These are bid items that have been proven useful in recent projects but have not yet been incorporated into Standard Bid Items. They do, however, have Standardized Special Provisions written for them which are incorporated in the project special provisions. STSP pay items will be given a standard seven digit number, if appropriate, once it is developed and will end with an ".S" to designate the spec language is still a special provision. They are explained in FDM 19-15-85.
- Project Special Provision Bid Items: These are bid items that have been set up for a specific project. They have no pre-established documentation and they must be fully explained in the project special provisions. Special Provisions will be numbered with an "SPV" prefix and be designated with a unique unit of measure. Similar to the current policy if more than one of that item number is needed in a project it will contain a unique description that is sequentially numbered between items. Refer to Creating an Estimate in Estimator: AASHTOWare Project Non-Standard Item Numbers table for a list item numbers and their associated unit of measure.
A category is a group of bid items in a project that are grouped together for one of the following reasons:
- All the bid items have the same funding arrangements or
- All the bid items are associated with the same federal work type o
- All the bid items are incorporated within a specific portion of work such as a category for each structure, the roadway items, etc.
Bid items are grouped by funding arrangements to ensure that all the agencies, that are paying for the work, will pay only their fair share. This means the same bid item may appear in more than one category if different quantities of it are paid for in different ways. For example, a contract may involve work in both rural and urban areas. The rural section may be funded by a combination of federal and state funds while the urban section may have a combination of federal/state/local funding. In this case, those bid items common to both areas will be apportioned by quantity to two different categories. Field staff will then report the accomplishment of work by category so local agencies will pay for only that work they agreed to pay for and only when it is done. Funding arrangements are established in the Financial Integrated Improvement Programming System (FIIPS). Designers will need to get the funding information from FIIPS to complete the funding for the estimate in AASHTOWare Project Preconstruction.
FHWA requires the department to keep records on how federal-aid highway funds are spent. To do this, FHWA has created a set of work types and the department reports work accomplished in each of these types. Refer to the Federal Work Category Table for a complete list of federal work type codes. Just like categories, federal work types can encompass numerous bid items. For example, federal work type 01 is New Construction Roadway work.
Each category has its own numerical code that was determined in FIIPS when they are establishing the project funding. Category numbering normally starts with 0010 and continues with other categories (e.g., 0020, 0030, etc.).
Tip: Remember, categories are set up for different funding situations as well as different federal work types. Another point to remember, category numbering is associated with a project. If a proposal has more than one project, the category numbering starts over with 0010 for the second project.
A project estimate is the accumulation of categories and their associated bid items. A simple project may have only one category of bid items, while a complex project may have numerous categories to fully describe the project’s situation. See the division's policy on confidentially for project estimates below.
The following statements are the division’s policy on the confidential nature of estimates:
- Final estimates of project costs based on estimated prices are confidential and for internal use by the department and FHWA personnel.
- Final estimates of project costs based on estimated unit prices remain confidential after bids are received.
- A report showing total estimated cost of projects by ranges, will be available from the Bureau of State Highway Programs to the public, upon request. The ranges may be modified to fit changing conditions upon approval of the administrator.
- For projects with participation by local governmental agencies, the final estimated cost of the project, based on estimated unit prices, should be rounded off to even amounts before being communicated to the sponsoring local government.
- For situations not covered above, employees may use their discretion in releasing accurate final estimated costs. Keep in mind statements 1-4 above and that the final estimates are held confidential from the general public.
A proposal is a contract that has not yet been signed by the governor. This is the level of PS&E organization that is LET to bid. In simple situations, a proposal may consist of only one project. In more complex situations, a proposal may consist of several projects that have been combined for bidding purposes.
Sometimes projects contain a single bid item that occurs several times on a project (e.g., Deck Drains [structure]). In these cases, it is important for contractors to be able to establish individual bids for each individual occurrence of the item. In other cases, a single bid item may occur several times on a project but has one quantity at the proposal level because it is prorated among funding categories (e.g., Field Office Type A).
Prorating is the process of subdividing a single bid item into fractional portions of one within a project and allocating these portions to certain categories of work based on their funding arrangements or to different projects within the same proposal (e.g., Mobilization).
Never prorate an item with the unit of measure of Lump Sum. The quantity of a Lump Sum item must ALWAYS be 1.0. For an item that cannot be prorated between categories of a project or proposal, use the same standard bid item number with an unique supplemental description in each required category.
The supplemental description will follow this format:
Special provision list number (i.e., 01., 02., 03., etc.) followed by the supplemental description detail identified in the parentheses of the standard bid item (i.e., station, parcel, project, structure, etc.).
Example:
206.1000 Exc for Structure Bridges (structure) 1.0 LS
02. B-15-0069206.1000 Exc for Structure Bridges (structure) 1.0 LS
04. B-15-0076Each item would have a quantity of 1.0 LS and not be added together at the proposal level.
- Numbers at the beginning of supplemental description do not have to be sequential, but each item that contains ( ) in its title must always begin its supplemental description with a number.
- If one or more projects are contained in the proposal, the numbers in the supplemental description for an item should not be duplicated.
Certain items such as Traffic Control, Field Office, Field Laboratory, Finishing Roadway, and Maintenance and Repair of Haul Roads can be prorated among categories of a project. Use the standard bid item number with the same supplemental description in each required category of the project.
The supplemental description will follow this format:
The same special provision list number for all items, within a project, (i.e., 01., 02., 03., etc.) followed by the supplemental description detail identified in the parenthesizes of the standard bid item (i.e., station, parcel, project, structure, etc.). The supplemental description for each item within a project must be exactly alike so that they are combined at the proposal level. You can only prorate items out to two decimal places.
Example:
Project 1
Category 0010
213.0100 Finishing Roadway (project) 0.3 EACH
01. 1000-00-71Category 0020
213.0100 Finishing Roadway (project) 0.7 EACH
01. 1000-00-71Project 2
Category 0010
213.0100 Finishing Roadway (project) 1.0 EACH
02. 1001-01-72
Requirement: Each item must add up to 1.0 EACH per project at the proposal level.
619.1000 Mobilization is the only bid item that must be prorated among multiple projects in a contract. In addition, the mobilization item can be prorated between categories within a project:
- Categories representing major portions of the project should always have the mobilization item included.
- Categories representing minor portions of work can receive a prorated portion of the mobilization item when appropriate.
Info: Prorated items should never be carried out beyond two places to the right of the decimal point. The Field Office bid item can follow this same rule if necessary.
Example:
Project 1
Category 0010
619.1000 Mobilization 0.25 EACHCategory 0020
619.1000 Mobilization 0.25 EACHProject 2
Category 0010
619.1000 Mobilization 0.25 EACHCategory 0020
619.1000 Mobilization 0.25 EACH
Requirement: Each item may have a quantity of 0.25 and adds up to 1.0 EACH at the proposal level.
Beginning with the November 2022 bid letting, always use Each instead of Lump Sum as the unit of measurement for Special Provision items. Use of Lump Sum items in the Special Provisions should be approved by the Bureau of Project Development.
Prorated / Contract | Prorated / Project | Number | Unit | Description |
X | 213.0100 | EACH | Finishing Roadway (project) | |
X | 618.0100 | EACH | Maintenance and Repair of Haul Roads (project) | |
X | 619.1000 | EACH | Mobilization | |
X | X | 642.5001 | EACH | Field Office Type B |
X | X | 642.5201 | EACH | Field Office Type C |
X | X | 642.5401 | EACH | Field Office Type D |
X | X | 642.6001 | EACH | Field Laboratory |
X | X | 643.5000 | EACH | Traffic Control |