Diaries

Last updated: 2026-02-04

Project Engineers are required to create a diary for each day of the week including Saturdays, Sundays, and holidays unless time is suspended (Available Time Working Day contracts only). If no work is done by the contractor or subcontractor, that should be noted in the diary (e.g. "No work").

If daily diaries are not entered on a regular basis, Compliance Specialists are unable to accurately monitor and identify possible discrepancies for the contractor and subcontractors working on the project on a weekly or bi-weekly basis.