Diary adjustments for Working Day sites

Last updated: 2023-11-30

Roles:

  • Project Engineer = modify access
  • Contract Specialist, Project Manager, Supervisor, Chief, Inspector, FHWA, ReadonlyConstr = Readonly access
  • Contractors = No access

Time can be adjusted on a locked diary to correct a diary time charge on an approved payment estimate using the Diary Adjustments tab.

Info:
  • Diary adjustments can only be made on working day sites.
  • If project staff need to make a diary adjustment for the start date of the contract (Time Charges Start Date) and are unable to locate the diary date on the Select Diary Contract Time Charges component, please check the Time Charges Start Date for the working day site. If the Time Charges Start Date on the Main 00 Site reflects a time other 12:00:00 AM adjust the time to 12:00:00 AM.