Adjusting contract time

(Including Extending, Reducing or Suspending Time)

Last updated: 2023-08-24

Roles:

  • Contract Specialist, Project Engineer = modify access
  • Contractor, Project Manager, Supervisor, Chief, Inspector, FHWA, ReadonlyConstr, UtilityCoordinator = read only access

Here is guidance for project staff to follow to extend or suspend time on a contract site if there is an excusable delay that affects the controlling item of work.

  • Contract time will be extended on a change order for completion date or calendar day sites. On working day sites, time charges will be delayed. In all of these circumstances, liquidated damages are placed on hold while processing a time extension or delaying contract time.
  • Time can be suspended on working days sites as has been done in the past.

In addition, there is guidance to reduce and change time on a contract site.

Warning: Work closely with the Project Manager and Contract Specialist during this process.

Info:
  • If the Actual Completion (Time Charges Stop Date) on the site record exceeds the Current Completion Date, liquidated damages will be assessed on the next payment estimate.
  • In AWP Construction, the Contract Specialist cannot change the following fields after the first payment estimate has been submitted and approved on the contract. If one or more of these fields were entered or calculated in error, please contact the AWP System Administrators for assistance. They may be able to make a database adjustment depending upon the situation.
    • Original Completion Date
    • Original Number of Time Units
    • Adjusted Number of Time Units
    • Liquidated Damages Rate, Disincentive Rate, Incentive Rate
    • Liquidated Damages Cap Amount, Disincentive Cap Amount, Incentive Cap Amount
      (These fields were known as Max Liquid Dam. Rte. in the legacy system.)

Instructions are provided for the following situations: