Daily Work Reports (DWRs)

Last updated: 2024-10-10

Roles:

  • Project Engineer = modify access
  • Contract Specialist, Project Manager, Supervisor, Chief, FHWA, ReadonlyConstr = Readonly access
  • Contractors = No access
Requirements:
  • Daily Work Reports (DWRs) are REQUIRED for each day that a contractor works at the job site. Input must include the following fields:
    • Weather
    • Inspector's comments
    • Men and hours for the contractor and subcontractors present at the job site.
  • Project Engineers and Inspectors should discuss data entry requirements for DWRs with their Project Manager for each contract.
  • Project Engineers and Inspectors should discuss the DWR approval process to determine if the inspector will approve their own DWRs or if the Project Engineer will review and approve all DWRs for this contract. Go to Daily Work Report (DWR) Approval Process for more details.
  • Added the ability to view and search the DWR Comment on the Contract Progress Summary Daily Work Reports component. It is recommended that Project Engineers enter a single "DWRComment - DWR Comment" as the last updated DWR Comment is the one that will appear in the list. More details about this process appear below on the General tab.
  • It is recommended that project staff review CMM 160 - Construction Inspection prior to creating DWRs and diaries.

 

Warnings:
  • Item overruns - The Project Engineer should notify the Project Manager about item overruns identified when saving an DWR and what estimate the DWR items will be associated to. During the payment estimate review process, the Project Manager should review the Payment Estimate Summary By Project Report for items with a percent complete over 100%. The payment estimate and associated DWR can be placed back in draft status if item posting changes are needed.
  • Warning: Detected rows with warnings. Please review messages below.

    • Prj ####-##-##, Prj Item Ln 0006, Cont Item Ln 0010: Qty Posted to Date of 29.000 exceeds Current Qty of 24.000 by 5.0000
    • Prj ####-##-##, Prj Item Ln 0006, Cont Item Ln 0010: Qty Posted to Date of 38.000 exceeds Current Qty of 33.000 by 5.000
    • Prj ####-##-##, Prj Item Ln 0012, Cont Item Ln 0028: Qty Posted to Date of 419.000 exceeds Current Qty of 410.000 by 9.000

  • When DWRs are synced from Mobile Inspector to AWP Construction, they are always in Pending Approval status awaiting the Project Engineer's approval.
  • Once a Daily Work Report (DWR) is approved and associated to a payment estimate, it is locked. No fields can be edited on the DWR.
    • A new DWR MUST be created to offset any item posting errors, equipment or personnel selection errors, or to add additional comments that were not part of the original DWR.
    • A new DWR MUST be created to enter additional item posting remarks for finals.
      For example, create a 0 quantity item posting and enter “Final Quantity See Sheet 1234.01".
  • Once a diary is associated to a payment estimate, it is locked. Only the Diary remarks can be edited. No other fields can be edited.
  • Additional DWRs can be created at a later date to document missing information under equipment, personnel or DWR comments and tied to a locked diary. Once these DWRs are approved, they will be tied to the corresponding diary appearing on the DWRs tab. If the Daily Diary Report is recreated, the new DWR will appear on the report too.
  • Field staff have the option to approve DWRs with item postings only (for payment estimates) leaving the other DWRs in draft status so they can be edited in the future (e.g. update DWR remarks).


Daily Work Report (DWR) data entry is broken down into these key areas: