Payment estimate review and approval process

Last updated: 2024-03-20

Roles:

  • Project Engineer and Project Manager = modify access
  • Contract Specialist, Inspector, Supervisor, Chief, FHWA, ReadonlyConstr = Readonly access

Payment estimates are approved in AWP Construction based on the payment estimate types and approval levels setup by the AASHTOWare Project System Administrators. A payment estimate will begin the approval process when the Project Engineer creates and approves the draft payment estimate. Staff will receive a system event email notification when it is their role's turn to approve the payment estimate.

Warning: Once final approval is received for a payment estimate, the payment estimate CANNOT be altered or deleted. A new payment estimate is required to make any corrections or changes to the contract.

Info:
  • There are four types of payment estimates - Intermediate, Semi-Final, Final, Post-Final 
    • Post-Final payment estimates are used only when an additional estimate is required after the final estimate. Discuss using this estimate type with the region Contract Specialist and the AASHTOWare Project System Administrators.
  • Two roles approve all payment estimate types - Project Engineer and Project Manager.
  • There are four payment estimate statuses - Draft, Pending Approval, Approved and Rejected.
  • As of January 24, 2022, liquidated damages are calculated on both the main 00 site and all interim sites. There is a line item on the Payment Estimate Report for liquidated damages. The line item on the Payment Estimate Report for disincentives will no longer be used for contracts withholding liquidated damages from this date forward; however, contracts that previously charged disincentives on any interim sites will continue to do so throughout the life of the contract.
    • Incentive and disincentive pay items are still available.
    • Disincentive pay items will not be included in the disincentive line item on the payment estimate.

 

The Payment Estimate Approval process begins when the Project Engineer both submits the payment estimate for approval and approves the payment estimate. The next approver will receive a system event email notification notifying them that it is their role's turn to approve the payment estimate. Payment Estimate review and approval is broken down into these key areas: